This study examines the economic consequences of building the Black Hills Energy natural gas-fired power plant with a project labor agreement (PLA). The academic research on the costs of project labor agreements is discussed. The study also examines the economic impact on Pueblo County if the project were built with and without a PLA. The results of the study are summarized.
study conducted by the Healy Center for Business and Economic Research, Colorado State University-Pueblo ; Kevin Duncan. "June 10, 2010." Online resource; title from PDF cover (viewed November 2018)
Fossil fuel power plants--Economic aspects Economic aspects Collective labor agreements
Black Hills Energy Power Plant (Pueblo, Colo.).
Colorado
1 online resource (12 pages)
eng
UCSP6/1.2/B56/2010/INTERNET
http://hdl.handle.net/11629/co:28790
1076273433
2018-11-30T19:57:16.330Z